| Assessment Year | 2001 |
|---|---|
| Principal Product | Biomedical Instruments |
| NAICS |
n/a
|
| SIC | 3826: Laboratory Analytical Instruments |
| Sales Range | $50 M to 100M |
| # of Employees | 220 |
| Plant Area |
67,868
ft2
|
| Annual Production | 2,400
pieces
|
| Production Hrs. Annual | 2,750
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $59,839 | 1,866,600 |
kWh
|
$0.032 |
| Electricity Demand | $34,140 | 3,996 |
kW-mo/yr
|
$8.54 |
| Electricity Fees | $6,745 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $114,618 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,711 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.448: Install automatic part storage / retreval system | $82,500 | $120,000 | - | - | $82,500 | |
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $20,523 | - |
$16,111
476,661
kWh
|
$4,412
-
kW-mo/yr
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $7,035 | $9,500 |
$5,522
163,374
kWh
|
$1,513
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,569 | $16,804 |
$1,777
52,583
kWh
|
$1,792
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $188 | $630 |
$147
4,354
kWh
|
$41
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $118 | $450 |
$118
3,510
kWh
|
- | - | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $685 | $3,600 |
$685
20,258
kWh
|
- | - | |
| TOTAL RECOMMENDED | $114,618 | $150,984 |
$24,360
720,740
kWh
|
$7,758
-
kW-mo/yr
|
$82,500 | ||
| TOTAL IMPLEMENTED | $20,711 | $630 |
$16,258
481,015
kWh
|
$4,453
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs