Assessment Year | 1996 |
---|---|
Principal Product | Bottles |
NAICS |
n/a
|
SIC | 2842: Specialty Cleaning, Polishing, and Sanitation Preparations |
Sales Range | $5 M to 10M |
# of Employees | 28 |
Plant Area |
34,000
ft2
|
Annual Production | 34,543,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $250,505 | 4,092,614 |
kWh
|
$0.061 |
Electricity Demand | $44,644 | 9,815 |
kW-mo/yr
|
$4.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,106 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,041 | $3,571 |
$1,811
29,601
kWh
|
$230
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $980 | $684 |
$896
14,654
kWh
|
$84
-
kW-mo/yr
|
|
03 | 2.4133: Use most efficient type of electric motors | $4,485 | $5,221 |
$3,726
60,961
kWh
|
$759
-
kW-mo/yr
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,600 | $700 |
$1,600
22,274
kWh
|
- | |
TOTAL RECOMMENDED | $9,106 | $10,176 |
$8,033
127,490
kWh
|
$1,073
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $1,600 | $700 |
$1,600
22,274
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs