Assessment Year | 2001 |
---|---|
Principal Product | Bag Making Equipment |
NAICS |
n/a
|
SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
40,200
ft2
|
Annual Production | 30
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $20,701 | 710,141 |
kWh
|
$0.029 |
Electricity Demand | $9,950 | 1,913 |
kW-mo/yr
|
$5.20 |
Electricity Fees | $1,750 | - |
|
- |
Natural Gas | $8,878 | 1,716 |
MMBtu
|
$5.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,279 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,956 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $2,193 | $1,000 | - | - | - | - | - | $2,193 | |
02 | 2.7261: Install timers and/or thermostats | $1,900 | $1,000 | - | - |
$1,900
-
MMBtu
|
- | - | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $1,195 | - | - | - | - | - | $1,195 | - | |
04 | 3.8121: Cover containers to minimize evaporative losses | $918 | $1,000 | - | - | - | $900 | - | $18 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $456 | $1,895 |
$325
10,551
kWh
|
$131
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $210 | $150 |
$210
6,741
kWh
|
- | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $137 | $90 |
$98
3,224
kWh
|
$39
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $270 | $120 |
$192
6,155
kWh
|
$78
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $7,279 | $5,255 |
$825
26,671
kWh
|
$248
-
kW-mo/yr
|
$1,900
-
MMBtu
|
$900 | $1,195 | $2,211 | ||
TOTAL IMPLEMENTED | $4,956 | $4,105 |
$615
19,930
kWh
|
$248
-
kW-mo/yr
|
$1,900
-
MMBtu
|
- | - | $2,193 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs