Assessment Year | 2001 |
---|---|
Principal Product | Machined Parts |
NAICS |
n/a
|
SIC | 3541: Machine Tools, Metal Cutting Types |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
67,000
ft2
|
Annual Production | 2,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $123,166 | 3,302,755 |
kWh
|
$0.037 |
Electricity Demand | $73,562 | 5,986 |
kW-mo/yr
|
$12.29 |
Electricity Fees | $13,237 | - |
|
- |
Natural Gas | $7,902 | 1,644 |
MMBtu
|
$4.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $229,288 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,863 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.424: Improve space comfort conditioning | $178,421 | $400,000 | n/a | - | - | - | - | - | $35,910 | $142,511 |
02 | 2.3134: Shift from daytime to nighttime operation | $24,138 | - | - |
$39,888
-
kW-mo/yr
|
- | - | - | $(-15,750.0) | - | |
03 | 2.7144: Install spectral reflectors / delamp | $9,794 | - |
$6,903
177,022
kWh
|
$2,891
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $4,726 | $1,994 |
$2,591
66,530
kWh
|
$2,135
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $712 | $2,050 |
$394
9,965
kWh
|
$318
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.7135: Install occupancy sensors | $418 | $300 |
$418
10,551
kWh
|
- | - | - | - | - | - | |
07 | 3.3131: Use evaporation to concentrate material | $8,770 | $16,000 | - | - |
$(-468.0)
-
MMBtu
|
$12,738
-
gal
|
- | $(-3,500.0) | - | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,292 | - | - | - | - | - |
$1,292
-
lb
|
- | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $630 | $640 |
$422
10,844
kWh
|
$208
-
kW-mo/yr
|
- | - | - | - | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $387 | $90 |
$259
6,741
kWh
|
$128
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $229,288 | $421,074 |
$10,987
281,653
kWh
|
$45,568
-
kW-mo/yr
|
$(-468.0)
-
MMBtu
|
$12,738
-
gal
|
$1,292
-
lb
|
$16,660 | $142,511 | ||
TOTAL IMPLEMENTED | $48,863 | $19,024 |
$10,593
271,688
kWh
|
$45,250
-
kW-mo/yr
|
$(-468.0)
-
MMBtu
|
$12,738
-
gal
|
- | $(-19,250.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs