ITAC Assessment: WI0359
ITAC logo
ITAC Assessment: WI0359
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Boiler Controls
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 150,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $122,367 2,940,211
kWh
Electricity Demand $98,119 7,851
kW-mo/yr
Electricity Fees $35,105 -
Natural Gas $59,954 14,420
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,323 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,522

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 3.8142: Distill contaminated solvents for reuse $6,185 $7,500 - - - $8,505
-
gal
$(-359.0)
-
lb
$(-726.0) $(-1,235.0) -
02 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $5,455 $24,000 $9,651
212,192
kWh
$9,186
-
kW-mo/yr
$(-13,382.0)
-
MMBtu
- - - - -
03 2.3134: Shift from daytime to nighttime operation $2,831 - - $7,556
-
kW-mo/yr
- - - $(-4,725.0) - -
04 2.2437: Recover waste heat from equipment $2,067 $1,000 - - $2,067
-
MMBtu
- - - - -
05 2.4221: Install compressor air intakes in coolest locations $1,815 $100 $1,224
26,964
kWh
$591
-
kW-mo/yr
- - - - - -
06 2.7144: Install spectral reflectors / delamp $1,781 - $1,289
28,429
kWh
$492
-
kW-mo/yr
- - - - - -
07 2.8113: Purchase gas directly from a contract gas supplier $1,391 $500 - - $1,391
-
MMBtu
- - - - -
08 3.2123: Convert to high volume low pressure (hvlp) paint guns $872 $1,000 - - - - - - - $872
09 2.7314: Reduce ventilation air $648 $500 $68
1,465
kWh
- $580
-
MMBtu
- - - - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $278 - $141
3,224
kWh
$137
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $23,323 $34,600 $12,373
272,274
kWh
$17,962
-
kW-mo/yr
$(-9,344.0)
-
MMBtu
$8,505
-
gal
$(-359.0)
-
lb
$(-5,451.0) $(-1,235.0) $872
TOTAL IMPLEMENTED $4,522 $600 $2,722
60,082
kWh
$1,220
-
kW-mo/yr
$580
-
MMBtu
- - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs