Assessment Year | 2007 |
---|---|
Principal Product | Concrete Pipe |
NAICS | 327310: Cement Manufacturing |
SIC | 3241: Cement, Hydraulic |
Sales Range | $10 M to 50M |
# of Employees | 33 |
Plant Area |
65,520
ft2
|
Annual Production | 80,000
ton
|
Production Hrs. Annual | 2,168
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $28,829 | 651,000 |
kWh
|
$0.044 |
Electricity Demand | $20,911 | 417 |
kW-mo/yr
|
$50.15 |
Natural Gas | $92,955 | 10,078 |
MMBtu
|
$9.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,867 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,085 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,718 | $500 |
$1,783
40,433
kWh
|
$935
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $896 | $100 |
$545
12,360
kWh
|
$351
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $364 | $25 |
$239
5,420
kWh
|
$125
-
kW-mo/yr
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $7,396 | $1,000 | - | - |
$7,396
-
MMBtu
|
|
05 | 2.7134: Use photocell controls | $386 | $55 |
$386
8,760
kWh
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $507 | $100 | - | - |
$507
-
MMBtu
|
|
07 | 2.7231: Use radiant heater for spot heating | $21,600 | $10,000 | - | - |
$21,600
-
MMBtu
|
|
TOTAL RECOMMENDED | $33,867 | $11,780 |
$2,953
66,973
kWh
|
$1,411
-
kW-mo/yr
|
$29,503
-
MMBtu
|
||
TOTAL IMPLEMENTED | $26,085 | $10,725 |
$2,567
58,213
kWh
|
$1,411
-
kW-mo/yr
|
$22,107
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs