Assessment Year | 1999 |
---|---|
Principal Product | Electric Heating Elements |
NAICS |
n/a
|
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $10 M to 50M |
# of Employees | 206 |
Plant Area |
392,300
ft2
|
Annual Production | 6,700,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $389,782 | 10,581,477 |
kWh
|
$0.037 |
Electricity Demand | $344,604 | 25,980 |
kW-mo/yr
|
$13.26 |
Electricity Fees | $69,963 | - |
|
- |
Natural Gas | $230,740 | 78,181 |
MMBtu
|
$2.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $260,616 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $98,121 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4114: Replace city water with recycled water via cooling tower | $97,790 | $44,000 |
$(-1,011.0)
(-24,912)
kWh
|
$(-832.0)
-
kW-mo/yr
|
- |
$99,633
-
Tgal
|
- | - | - | - | |
02 | 2.3134: Shift from daytime to nighttime operation | $92,705 | - | - |
$98,705
-
kW-mo/yr
|
- | - | - | - | $(-6,000.0) | - | |
03 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $54,425 | $102,000 |
$60,900
1,500,000
kWh
|
$43,860
-
kW-mo/yr
|
$(-50,335.0)
-
MMBtu
|
- | - | - | - | - | |
04 | 3.8142: Distill contaminated solvents for reuse | $7,803 | $13,900 | - | - | - | - |
$13,200
-
gal
|
$(-506.0)
-
lb
|
$(-3,591.0) | $(-1,300.0) | |
05 | 2.4221: Install compressor air intakes in coolest locations | $6,466 | $200 |
$3,293
81,184
kWh
|
$3,173
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 2.2511: Insulate bare equipment | $1,096 | $3,850 |
$485
12,016
kWh
|
$262
-
kW-mo/yr
|
$349
-
MMBtu
|
- | - | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $331 | $107 |
$231
5,569
kWh
|
$100
-
kW-mo/yr
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $260,616 | $164,057 |
$63,898
1,573,857
kWh
|
$145,268
-
kW-mo/yr
|
$(-49,986.0)
-
MMBtu
|
$99,633
-
Tgal
|
$13,200
-
gal
|
$(-506.0)
-
lb
|
$(-9,591.0) | $(-1,300.0) | ||
TOTAL IMPLEMENTED | $98,121 | $44,107 |
$(-780.0)
(-19,343)
kWh
|
$(-732.0)
-
kW-mo/yr
|
- |
$99,633
-
Tgal
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs