ITAC Assessment: OR0420
ITAC logo
ITAC Assessment: OR0420
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Custom machinery
NAICS
n/a
SIC 3549: Metalworking Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 14,533
pieces
Production Hrs. Annual 5,100
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $133,654 2,426,550
kWh
Electricity Demand $18,642 6,779
kW-mo/yr
Electricity Fees $3,412 -
Natural Gas $48,090 9,067
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,345 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,098

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 4.521: Clear and rent existing space $39,861 $1,920 $1,671
30,341
kWh
$50
-
kW-mo/yr
$5,500
-
MMBtu
$32,640 -
02 2.7111: Reduce illumination to minimum necessary levels $9,386 $530 $6,826
123,930
kWh
$802
-
kW-mo/yr
- $135 $1,623
03 2.7124: Make a practice of turning off lights when not needed $9,883 - $8,039
145,962
kWh
- - $142 $1,702
04 2.4226: Use / purchase optimum sized compressor $11,195 $5,000 $10,191
185,022
kWh
$1,004
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,020 $1,200 $3,600
65,280
kWh
$420
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $74,345 $8,650 $30,327
550,535
kWh
$2,276
-
kW-mo/yr
$5,500
-
MMBtu
$32,917 $3,325
TOTAL IMPLEMENTED $25,098 $6,200 $21,830
396,264
kWh
$1,424
-
kW-mo/yr
- $142 $1,702
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs