ITAC Assessment: WI0357
ITAC logo
ITAC Assessment: WI0357
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Aluminum Die Castings
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 113,200
ft2
Annual Production 23,500,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $568,902 7,186,401
kWh
Electricity Demand $220,318 16,142
kW-mo/yr
Electricity Fees $74,597 -
Natural Gas $273,324 78,774
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,168 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,686

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $42,443 $155,500 $42,443
1,012,896
kWh
- - - - - -
02 3.3131: Use evaporation to concentrate material $39,582 $76,000 - - $(-13,772.0)
-
MMBtu
$58,154
-
gal
- $(-4,800.0) -
03 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $25,236 $60,000 $33,939
810,082
kWh
$26,820
-
kW-mo/yr
$(-35,523.0)
-
MMBtu
- - - -
04 2.1221: Replace obsolete burners with more efficient ones $24,655 $10,800 - - $24,655
-
MMBtu
- - - -
05 2.4221: Install compressor air intakes in coolest locations $3,282 $1,580 $2,077
49,531
kWh
$1,205
-
kW-mo/yr
- - - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $900 $210 $587
14,068
kWh
$313
-
kW-mo/yr
- - - - -
07 3.8142: Distill contaminated solvents for reuse $2,963 $7,000 - - - $3,851
-
gal
$(-149.0)
-
lb
$(-300.0) $(-439.0)
08 3.5315: Lease / purchase baler; sell cardboard to recycler $2,702 $1,000 - - - - $2,702
-
lb
- -
09 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,780 - - - - - $1,780
-
lb
- -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $1,131 $4,017 $633
15,240
kWh
$498
-
kW-mo/yr
- - - - -
11 2.2511: Insulate bare equipment $494 $848 - - $494
-
MMBtu
- - - -
TOTAL RECOMMENDED $145,168 $316,955 $79,679
1,901,817
kWh
$28,836
-
kW-mo/yr
$(-24,146.0)
-
MMBtu
$62,005
-
gal
$4,333
-
lb
$(-5,100.0) $(-439.0)
TOTAL IMPLEMENTED $26,686 $15,027 $1,220
29,308
kWh
$811
-
kW-mo/yr
$24,655
-
MMBtu
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs