| Assessment Year | 1999 |
|---|---|
| Principal Product | Electro Mechanical and Refractory Fiber Products |
| NAICS |
n/a
|
| SIC | 3679: Electronic Components, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
110,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $33,305 | 1,000,293 |
kWh
|
$0.033 |
| Electricity Demand | $42,947 | 6,391 |
kW-mo/yr
|
$6.72 |
| Electricity Fees | $5,988 | - |
|
- |
| Natural Gas | $70,157 | 14,482 |
MMBtu
|
$4.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $62,565 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,362 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.521: Clear and rent existing space | $57,832 | $9,205 | - | - | - | $57,832 | |
| 02 | 2.2437: Recover waste heat from equipment | $2,018 | $1,200 | - | - |
$2,018
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,027 | $3,698 |
$568
16,120
kWh
|
$459
-
kW-mo/yr
|
- | - | |
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $757 | $500 | - | - |
$757
-
MMBtu
|
- | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $605 | $959 |
$307
8,792
kWh
|
$298
-
kW-mo/yr
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $326 | $1,380 |
$157
4,396
kWh
|
$169
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $62,565 | $16,942 |
$1,032
29,308
kWh
|
$926
-
kW-mo/yr
|
$2,775
-
MMBtu
|
$57,832 | ||
| TOTAL IMPLEMENTED | $1,362 | $1,459 |
$307
8,792
kWh
|
$298
-
kW-mo/yr
|
$757
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs