ITAC Assessment: WI0330
ITAC logo
ITAC Assessment: WI0330
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Industrial Sewing Machines
NAICS
n/a
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 508
Plant Area 452,000
ft2
Annual Production 15,000
pieces
Production Hrs. Annual 6,040
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $304,228 8,240,915
kWh
Electricity Demand $281,880 20,022
kW-mo/yr
Electricity Fees $31,804 -
Natural Gas $238,358 69,925
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $346,394 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $241,399

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.221: Use only amount of packaging material necessary $225,000 $10,000 - - - - - - - $225,000
02 4.423: Move product using mechanical means $71,911 $100,000 $(-2,095.0)
(-53,634)
kWh
$(-3,994.0)
-
kW-mo/yr
- - - $78,000 - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $11,610 $33,768 $7,404
189,918
kWh
$4,206
-
kW-mo/yr
- - - - - -
04 2.3135: Schedule routine maintenance during non-operating periods $11,095 - - $11,095
-
kW-mo/yr
- - - - - -
05 2.3134: Shift from daytime to nighttime operation $5,622 - - $5,622
-
kW-mo/yr
- - - - - -
06 3.2123: Convert to high volume low pressure (hvlp) paint guns $8,769 $4,000 - - - - $560
-
lb
- - $8,209
07 3.4114: Replace city water with recycled water via cooling tower $4,707 $15,000 $(-176.0)
(-4,396)
kWh
$(-133.0)
-
kW-mo/yr
- $5,516
-
Tgal
- $(-500.0) - -
08 3.4151: Minimize water usage $1,845 - - - - $1,845
-
Tgal
- - - -
09 4.821: Pay bills on time to avoid late fees $2,541 - - - - - - - $2,541 -
10 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,000 $5,000 - - - - $1,000
-
lb
- - -
11 2.4221: Install compressor air intakes in coolest locations $918 $640 $607
15,533
kWh
$311
-
kW-mo/yr
- - - - - -
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $873 $3,000 $873
22,274
kWh
- - - - - - -
13 2.2437: Recover waste heat from equipment $503 $500 - - $503
-
MMBtu
- - - - -
TOTAL RECOMMENDED $346,394 $171,908 $6,613
169,695
kWh
$17,107
-
kW-mo/yr
$503
-
MMBtu
$7,361
-
Tgal
$1,560
-
lb
$77,500 $2,541 $233,209
TOTAL IMPLEMENTED $241,399 $10,640 $607
15,533
kWh
$11,406
-
kW-mo/yr
- $1,845
-
Tgal
- - $2,541 $225,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs