| Assessment Year | 1998 |
|---|---|
| Principal Product | Cream Cheese and Butter |
| NAICS |
n/a
|
| SIC | 2020: |
| Sales Range | $50 M to 100M |
| # of Employees | 95 |
| Plant Area |
156,000
ft2
|
| Annual Production | 38,000,000
lb
|
| Production Hrs. Annual | 6,144
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $166,944 | 7,354,045 |
kWh
|
$0.023 |
| Electricity Demand | $113,533 | 15,702 |
kW-mo/yr
|
$7.23 |
| Electricity Fees | $3,765 | - |
|
- |
| Natural Gas | $245,374 | 64,076 |
MMBtu
|
$3.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $359,444 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,848 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.441: Install automatic packing equipment | $336,000 | $240,000 | - | - | - | $336,000 | - | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $7,848 | $500 | - | - |
$7,848
-
MMBtu
|
- | - | |
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $7,598 | $10,000 | - | - |
$7,598
-
MMBtu
|
- | - | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,590 | - | - |
$5,790
-
kW-mo/yr
|
- | $(-200.0) | - | |
| 05 | 4.321: Optimize production lot sizes and inventories | $1,652 | - | - | - | - | - | $1,652 | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $756 | $740 |
$368
15,240
kWh
|
$388
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $359,444 | $251,240 |
$368
15,240
kWh
|
$6,178
-
kW-mo/yr
|
$15,446
-
MMBtu
|
$335,800 | $1,652 | ||
| TOTAL IMPLEMENTED | $7,848 | $500 | - | - |
$7,848
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs