| Assessment Year | 1998 |
|---|---|
| Principal Product | Screws and cold headed fasteners |
| NAICS |
n/a
|
| SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
| Sales Range | $10 M to 50M |
| # of Employees | 104 |
| Plant Area |
77,000
ft2
|
| Annual Production | 250,000,000
pieces
|
| Production Hrs. Annual | 4,870
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $116,323 | 2,664,127 |
kWh
|
$0.044 |
| Electricity Demand | $85,185 | 6,990 |
kW-mo/yr
|
$12.19 |
| Electricity Fees | $4,485 | - |
|
- |
| Natural Gas | $16,733 | 4,484 |
MMBtu
|
$3.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,208 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,405 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,682 | $1,342 |
$778
17,878
kWh
|
$904
-
kW-mo/yr
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $986 | - |
$456
10,551
kWh
|
$530
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $597 | $2,250 |
$597
13,775
kWh
|
- | - | |
| 04 | 4.321: Optimize production lot sizes and inventories | $1,611 | - | - | - | $1,611 | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,138 | $740 |
$431
9,965
kWh
|
$707
-
kW-mo/yr
|
- | |
| 06 | 2.3132: Recharge batteries on during off-peak demand periods | $794 | - | - |
$794
-
kW-mo/yr
|
- | |
| 07 | 3.7137: Replace cloth rags with paper towels | $400 | - | - | - | $400 | |
| TOTAL RECOMMENDED | $7,208 | $4,332 |
$2,262
52,169
kWh
|
$2,935
-
kW-mo/yr
|
$2,011 | ||
| TOTAL IMPLEMENTED | $2,405 | - | - |
$794
-
kW-mo/yr
|
$1,611 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs