Assessment Year | 1998 |
---|---|
Principal Product | Drilling and Hammer Accessories |
NAICS |
n/a
|
SIC | 3546: Power-Driven Handtools |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
102,790
ft2
|
Annual Production | 180,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $92,187 | 2,203,107 |
kWh
|
$0.042 |
Electricity Demand | $204,591 | 14,616 |
kW-mo/yr
|
$14.00 |
Electricity Fees | $10,034 | - |
|
- |
Natural Gas | $124,640 | 34,083 |
MMBtu
|
$3.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,447 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,492 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $15,098 | $40,000 |
$5,847
133,060
kWh
|
$14,804
-
kW-mo/yr
|
$(-5,553.0)
-
MMBtu
|
- | |
02 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,699 | $5,024 |
$702
16,120
kWh
|
$997
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,492 | $7,504 |
$1,858
42,204
kWh
|
$2,634
-
kW-mo/yr
|
- | - | |
04 | 3.3122: Use filtration, centrifuging to remove contaminants | $3,414 | $7,000 | - | - | - | $3,414 | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,196 | - | - |
$2,196
-
kW-mo/yr
|
- | - | |
06 | 2.2511: Insulate bare equipment | $548 | $532 | - | - |
$548
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $27,447 | $60,060 |
$8,407
191,384
kWh
|
$20,631
-
kW-mo/yr
|
$(-5,005.0)
-
MMBtu
|
$3,414 | ||
TOTAL IMPLEMENTED | $4,492 | $7,504 |
$1,858
42,204
kWh
|
$2,634
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs