Assessment Year | 1997 |
---|---|
Principal Product | Compressors, pressure vessels, and package systems |
NAICS |
n/a
|
SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
Sales Range | $50 M to 100M |
# of Employees | 325 |
Plant Area |
400,000
ft2
|
Annual Production | 2,100
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $158,669 | 6,859,613 |
kWh
|
$0.023 |
Electricity Demand | $115,208 | 15,296 |
kW-mo/yr
|
$7.53 |
Electricity Fees | $5,666 | - |
|
- |
Natural Gas | $272,121 | 54,930 |
MMBtu
|
$4.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $98,212 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,690 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.621: Use fixtures to reduce machine changeout times | $28,500 | $4,500 | - | - | - | - | - | $30,000 | - | - | $(-1,500.0) | |
02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $21,896 | $55,000 |
$(-164.0)
(-6,741)
kWh
|
- | - | - | - | $(-1,500.0) | $23,560 | - | - | |
03 | 3.8142: Distill contaminated solvents for reuse | $16,529 | $30,000 | - | - | - |
$21,232
-
gal
|
$(-543.0)
-
lb
|
$(-2,860.0) | - | $(-1,300.0) | - | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $14,956 | $1,000 | - | - | - | - | - | - | - | $14,956 | - | |
05 | 3.4113: Treat and reuse rinse waters | $9,755 | $12,000 | - | - |
$19,305
-
gal
|
- |
$(-8,250.0)
-
lb
|
$(-1,300.0) | - | - | - | |
06 | 2.3191: Use demand controller or load shedder | $5,342 | $10,000 | - |
$5,342
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,234 | $740 |
$676
27,843
kWh
|
$558
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $98,212 | $113,240 |
$512
21,102
kWh
|
$5,900
-
kW-mo/yr
|
$19,305
-
gal
|
$21,232
-
gal
|
$(-8,793.0)
-
lb
|
$24,340 | $23,560 | $13,656 | $(-1,500.0) | ||
TOTAL IMPLEMENTED | $44,690 | $6,240 |
$676
27,843
kWh
|
$558
-
kW-mo/yr
|
- | - | - | $30,000 | - | $14,956 | $(-1,500.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs