Assessment Year | 1997 |
---|---|
Principal Product | Electric Resistors and Switches |
NAICS |
n/a
|
SIC | 3676: Electronic Resistors |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
165,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,375
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $214,446 | 5,791,032 |
kWh
|
$0.037 |
Electricity Demand | $226,949 | 15,971 |
kW-mo/yr
|
$14.21 |
Electricity Fees | $3,226 | - |
|
- |
Natural Gas | $69,466 | 19,060 |
MMBtu
|
$3.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $88,739 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,634 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $29,190 | $30,000 |
$13,331
342,614
kWh
|
$30,072
-
kW-mo/yr
|
$(-14,213.0)
-
MMBtu
|
- | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $2,867 | $1,480 |
$946
24,326
kWh
|
$1,921
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,444 | $120 |
$807
20,809
kWh
|
$637
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $25,193 | - | - |
$33,593
-
kW-mo/yr
|
- | - | $(-8,400.0) | - | |
05 | 4.441: Install automatic packing equipment | $24,000 | $20,000 | - | - | - | - | $24,000 | - | |
06 | 3.4114: Replace city water with recycled water via cooling tower | $3,119 | $18,000 |
$(-4,181.0)
(-55,979)
kWh
|
- | - |
$7,800
-
Tgal
|
$(-500.0) | - | |
07 | 3.4151: Minimize water usage | $2,100 | $1,000 | - | - | - |
$2,100
-
Tgal
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $686 | - |
$235
6,155
kWh
|
$451
-
kW-mo/yr
|
- | - | - | - | |
09 | 4.321: Optimize production lot sizes and inventories | $140 | - | - | - | - | - | - | $140 | |
TOTAL RECOMMENDED | $88,739 | $70,600 |
$11,138
337,925
kWh
|
$66,674
-
kW-mo/yr
|
$(-14,213.0)
-
MMBtu
|
$9,900
-
Tgal
|
$15,100 | $140 | ||
TOTAL IMPLEMENTED | $54,634 | $50,120 |
$14,138
363,423
kWh
|
$30,709
-
kW-mo/yr
|
$(-14,213.0)
-
MMBtu
|
- | $24,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs