| Assessment Year | 1997 |
|---|---|
| Principal Product | Leather |
| NAICS |
n/a
|
| SIC | 3111: Leather Tanning and Finishing |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
75,000
ft2
|
| Annual Production | 370,000
pieces
|
| Production Hrs. Annual | 6,275
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $49,614 | 1,864,009 |
kWh
|
$0.027 |
| Electricity Demand | $38,748 | 5,095 |
kW-mo/yr
|
$7.61 |
| Electricity Fees | $(-4,264.0) | - |
|
- |
| Natural Gas | $112,805 | 29,239 |
MMBtu
|
$3.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,153 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,261 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.441: Install automatic packing equipment | $24,000 | $19,000 | - | - | - | - | $24,000 | |
| 02 | 2.4131: Size electric motors for peak operating efficiency | $6,364 | $5,400 |
$1,912
68,581
kWh
|
$4,452
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,796 | - | - |
$3,796
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,479 | $6,750 |
$1,143
41,032
kWh
|
$1,336
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $725 | $1,608 |
$499
17,878
kWh
|
$226
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7314: Reduce ventilation air | $699 | $500 |
$69
2,345
kWh
|
- |
$630
-
MMBtu
|
- | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $617 | $640 |
$424
15,240
kWh
|
$193
-
kW-mo/yr
|
- | - | - | |
| 08 | 3.4151: Minimize water usage | $1,473 | $900 |
$(-1,293.0)
(-43,669)
kWh
|
- | - |
$2,766
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $40,153 | $34,798 |
$2,754
101,407
kWh
|
$10,003
-
kW-mo/yr
|
$630
-
MMBtu
|
$2,766
-
Tgal
|
$24,000 | ||
| TOTAL IMPLEMENTED | $9,261 | $8,408 |
$1,187
45,135
kWh
|
$4,678
-
kW-mo/yr
|
$630
-
MMBtu
|
$2,766
-
Tgal
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs