Assessment Year | 1997 |
---|---|
Principal Product | Display Fixtures |
NAICS |
n/a
|
SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
105,000
ft2
|
Annual Production | 600
units
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,910 | 1,361,665 |
kWh
|
$0.029 |
Electricity Demand | $38,584 | 4,391 |
kW-mo/yr
|
$8.79 |
Electricity Fees | $219 | - |
|
- |
Natural Gas | $36,514 | 7,623 |
MMBtu
|
$4.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,816 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $5,567 | $500 | - | - | - | - | - | $5,567 | |
02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,058 | - | - | - | - |
$2,058
-
lb
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,683 | $7,800 |
$1,683
55,686
kWh
|
- | - | - | - | - | |
04 | 3.8122: Use tight-fitting lids on material containers to reduce voc emissions | $1,240 | $1,000 | - | - |
$115
-
gal
|
- | $1,125 | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $1,064 | $640 |
$632
21,102
kWh
|
$432
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.3132: Recharge batteries on during off-peak demand periods | $1,008 | $5,000 | - |
$1,008
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $183 | $455 |
$83
2,931
kWh
|
$100
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $12,803 | $15,395 |
$2,398
79,719
kWh
|
$1,540
-
kW-mo/yr
|
$115
-
gal
|
$2,058
-
lb
|
$1,125 | $5,567 | ||
TOTAL IMPLEMENTED | $8,816 | $5,955 |
$83
2,931
kWh
|
$1,108
-
kW-mo/yr
|
- |
$2,058
-
lb
|
- | $5,567 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs