ITAC Assessment: WI0288
ITAC logo
ITAC Assessment: WI0288
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Display Fixtures
NAICS
n/a
SIC 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 105,000
ft2
Annual Production 600
units
Production Hrs. Annual 4,500
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,910 1,361,665
kWh
Electricity Demand $38,584 4,391
kW-mo/yr
Electricity Fees $219 -
Natural Gas $36,514 7,623
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,803 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,816

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $5,567 $500 - - - - - $5,567
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,058 - - - - $2,058
-
lb
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,683 $7,800 $1,683
55,686
kWh
- - - - -
04 3.8122: Use tight-fitting lids on material containers to reduce voc emissions $1,240 $1,000 - - $115
-
gal
- $1,125 -
05 2.4221: Install compressor air intakes in coolest locations $1,064 $640 $632
21,102
kWh
$432
-
kW-mo/yr
- - - -
06 2.3132: Recharge batteries on during off-peak demand periods $1,008 $5,000 - $1,008
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $183 $455 $83
2,931
kWh
$100
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $12,803 $15,395 $2,398
79,719
kWh
$1,540
-
kW-mo/yr
$115
-
gal
$2,058
-
lb
$1,125 $5,567
TOTAL IMPLEMENTED $8,816 $5,955 $83
2,931
kWh
$1,108
-
kW-mo/yr
- $2,058
-
lb
- $5,567
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs