| Assessment Year | 1996 |
|---|---|
| Principal Product | Specialty Motors |
| NAICS |
n/a
|
| SIC | 3621: Motors and Generators |
| Sales Range | $10 M to 50M |
| # of Employees | 400 |
| Plant Area |
500,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $213,121 | 8,615,768 |
kWh
|
$0.025 |
| Electricity Demand | $191,130 | 27,638 |
kW-mo/yr
|
$6.92 |
| Electricity Fees | $22,714 | - |
|
- |
| Natural Gas | $238,833 | 71,742 |
MMBtu
|
$3.33 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $62,930 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,504 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $18,544 | $3,400 | - | - |
$18,544
-
MMBtu
|
- | - | - | - | |
| 02 | 3.4114: Replace city water with recycled water via cooling tower | $12,559 | $30,000 |
$(-2,909.0)
(-111,958)
kWh
|
$(-1,732.0)
-
kW-mo/yr
|
- |
$17,700
-
Tgal
|
- | $(-500.0) | - | |
| 03 | 2.3191: Use demand controller or load shedder | $7,523 | - | - |
$7,523
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $4,862 | $27,740 |
$(-1,461.0)
(-56,272)
kWh
|
$(-1,118.0)
-
kW-mo/yr
|
$7,441
-
MMBtu
|
- | - | - | - | |
| 05 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $4,439 | $1,000 | - | - | - | - |
$825
-
lb
|
- | $3,614 | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $4,075 | - |
$2,817
108,441
kWh
|
$1,258
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,216 | $1,779 |
$1,529
58,910
kWh
|
$687
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 2.2621: Modify refrigeration system to operate at a lower pressure | $2,917 | $9,000 |
$1,609
61,841
kWh
|
$1,308
-
kW-mo/yr
|
- | - | - | - | - | |
| 09 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $2,700 | - | - | - | - | - | - | $2,700 | - | |
| 10 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,744 | $15,000 |
$10,998
422,919
kWh
|
$7,795
-
kW-mo/yr
|
$(-16,049.0)
-
MMBtu
|
- | - | - | - | |
| 11 | 2.7314: Reduce ventilation air | $351 | $500 |
$194
7,327
kWh
|
- |
$157
-
MMBtu
|
- | - | - | - | |
| TOTAL RECOMMENDED | $62,930 | $88,419 |
$12,777
491,208
kWh
|
$15,721
-
kW-mo/yr
|
$10,093
-
MMBtu
|
$17,700
-
Tgal
|
$825
-
lb
|
$2,200 | $3,614 | ||
| TOTAL IMPLEMENTED | $11,504 | $30,019 |
$3,079
118,406
kWh
|
$827
-
kW-mo/yr
|
$7,598
-
MMBtu
|
- | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs