ITAC Assessment: WI0279
ITAC logo
ITAC Assessment: WI0279
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Specialty Motors
NAICS
n/a
SIC 3621: Motors and Generators
Sales Range $10
M
to 50
M
# of Employees 400
Plant Area 500,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,121 8,615,768
kWh
Electricity Demand $191,130 27,638
kW-mo/yr
Electricity Fees $22,714 -
Natural Gas $238,833 71,742
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $62,930 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,504

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings
01 2.7261: Install timers and/or thermostats $18,544 $3,400 - - $18,544
-
MMBtu
- - - -
02 3.4114: Replace city water with recycled water via cooling tower $12,559 $30,000 $(-2,909.0)
(-111,958)
kWh
$(-1,732.0)
-
kW-mo/yr
- $17,700
-
Tgal
- $(-500.0) -
03 2.3191: Use demand controller or load shedder $7,523 - - $7,523
-
kW-mo/yr
- - - - -
04 2.7243: Improve air circulation with destratification fans / other methods $4,862 $27,740 $(-1,461.0)
(-56,272)
kWh
$(-1,118.0)
-
kW-mo/yr
$7,441
-
MMBtu
- - - -
05 3.2123: Convert to high volume low pressure (hvlp) paint guns $4,439 $1,000 - - - - $825
-
lb
- $3,614
06 2.7111: Reduce illumination to minimum necessary levels $4,075 - $2,817
108,441
kWh
$1,258
-
kW-mo/yr
- - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,216 $1,779 $1,529
58,910
kWh
$687
-
kW-mo/yr
- - - - -
08 2.2621: Modify refrigeration system to operate at a lower pressure $2,917 $9,000 $1,609
61,841
kWh
$1,308
-
kW-mo/yr
- - - - -
09 3.5248: Separate and recycle scrap metal to foundry or for sale $2,700 - - - - - - $2,700 -
10 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,744 $15,000 $10,998
422,919
kWh
$7,795
-
kW-mo/yr
$(-16,049.0)
-
MMBtu
- - - -
11 2.7314: Reduce ventilation air $351 $500 $194
7,327
kWh
- $157
-
MMBtu
- - - -
TOTAL RECOMMENDED $62,930 $88,419 $12,777
491,208
kWh
$15,721
-
kW-mo/yr
$10,093
-
MMBtu
$17,700
-
Tgal
$825
-
lb
$2,200 $3,614
TOTAL IMPLEMENTED $11,504 $30,019 $3,079
118,406
kWh
$827
-
kW-mo/yr
$7,598
-
MMBtu
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs