ITAC Assessment: WI0261
ITAC logo
ITAC Assessment: WI0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Racks for automobile shops and accessories for the racks
NAICS
n/a
SIC 2569:
Sales Range $50
M
to 100
M
# of Employees 69
Plant Area 80,000
ft2
Annual Production 700
pieces
Production Hrs. Annual 2,425
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,838 934,349
kWh
Electricity Demand $27,060 3,788
kW-mo/yr
Electricity Fees $9,622 -
Natural Gas $38,567 7,841
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,101 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,630

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.7314: Reduce ventilation air $4,065 $1,000 - - - $4,065
-
MMBtu
-
02 2.6232: Install set-back timers $4,026 $1,200 - - - $4,026
-
MMBtu
-
03 2.8121: Apply for tax-free status for energy purchases $3,491 - - - $3,491 - -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $3,300 $5,000 - - - - $3,300
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $113 - $53
2,052
kWh
$60
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $106 $56 $46
1,758
kWh
$60
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $15,101 $7,256 $99
3,810
kWh
$120
-
kW-mo/yr
$3,491 $8,091
-
MMBtu
$3,300
TOTAL IMPLEMENTED $7,630 $1,200 $53
2,052
kWh
$60
-
kW-mo/yr
$3,491 $4,026
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs