Assessment Year | 2001 |
---|---|
Principal Product | Commercial Printing |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
60,000
ft2
|
Annual Production | 250,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $67,624 | 2,621,080 |
kWh
|
$0.026 |
Electricity Demand | $87,993 | 8,340 |
kW-mo/yr
|
$10.55 |
Electricity Fees | $6,509 | - |
|
- |
Natural Gas | $13,691 | 7,719 |
MMBtu
|
$1.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $206,835 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,218 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $947 | $308 |
$565
21,900
kWh
|
$382
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,735 | $180 |
$4,319
167,400
kWh
|
$2,416
-
kW-mo/yr
|
- | - | - | |
03 | 4.652: Replace existing equipment with more suitable substitutes | $193,540 | $25,975 | - | - | - | $193,540 | - | |
04 | 2.7229: Air condition only space necessary | $4,536 | $400 | - | - |
$4,536
-
MMBtu
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $190 | - |
$190
7,352
kWh
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $495 | $374 |
$85
3,294
kWh
|
$57
-
kW-mo/yr
|
- | $166 | $187 | |
07 | 2.7135: Install occupancy sensors | $392 | $627 |
$392
15,205
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $206,835 | $27,864 |
$5,551
215,151
kWh
|
$2,855
-
kW-mo/yr
|
$4,536
-
MMBtu
|
$193,706 | $187 | ||
TOTAL IMPLEMENTED | $12,218 | $888 |
$4,884
189,300
kWh
|
$2,798
-
kW-mo/yr
|
$4,536
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs