Assessment Year | 1996 |
---|---|
Principal Product | Variable frequency drives |
NAICS |
n/a
|
SIC | 3625: Relays and Industrial Controls |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
500,000
ft2
|
Annual Production | 20,000
pieces
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,478 | 1,000,879 |
kWh
|
$0.035 |
Electricity Demand | $31,762 | 2,810 |
kW-mo/yr
|
$11.30 |
Electricity Fees | $(-536.0) | - |
|
- |
Natural Gas | $3,177 | 747 |
MMBtu
|
$4.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,996 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,977 | - | - |
$7,977
-
kW-mo/yr
|
- | - | |
02 | 2.7251: Reduce air conditioning load by evaporating water from roof | $5,468 | $15,000 |
$3,598
96,717
kWh
|
$3,587
-
kW-mo/yr
|
$(-1,717.0)
-
Tgal
|
- | |
03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $2,982 | $7,000 | - | - | - |
$2,982
-
lb
|
|
04 | 2.4239: Eliminate or reduce compressed air usage | $2,323 | $3,075 |
$2,323
62,427
kWh
|
- | - | - | |
05 | 2.7144: Install spectral reflectors / delamp | $1,246 | - |
$734
19,637
kWh
|
$512
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $19,996 | $25,075 |
$6,655
178,781
kWh
|
$12,076
-
kW-mo/yr
|
$(-1,717.0)
-
Tgal
|
$2,982
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs