Assessment Year | 2013 |
---|---|
Principal Product | Frozen Hamburgers and Cheeseburgers |
NAICS | 311611: Animal (except Poultry) Slaughtering |
SIC | 2011: Meat Packing Plants |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
65,000
ft2
|
Annual Production | 20,600,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $295,309 | 6,914,400 |
kWh
|
$0.043 |
Electricity Demand | $167,093 | 13,988 |
kW-mo/yr
|
$11.95 |
Electricity Fees | $2,603 | - |
|
- |
Natural Gas | $118,081 | 18,278 |
MMBtu
|
$6.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,045 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $58,045 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $9,148 | $1,000 | - | - | $9,148 | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,605 | $19,350 |
$2,614
61,200
kWh
|
$1,586
-
kW-mo/yr
|
- | - | $405 | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,136 | $7,000 |
$1,424
33,348
kWh
|
$544
-
kW-mo/yr
|
- | - | $168 | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $11,400 | $19,000 |
$9,740
228,057
kWh
|
$1,660
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $936 | $500 |
$1,085
25,397
kWh
|
$451
-
kW-mo/yr
|
- | - | - | $(-600.0) | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,058 | $500 | - | - | - |
$6,058
-
MMBtu
|
- | - | |
07 | 2.7224: Reduce space conditioning during non-working hours | $7,470 | - |
$1,094
25,625
kWh
|
- | - |
$6,376
-
MMBtu
|
- | - | |
08 | 2.2628: Utilize a less expensive cooling method | $8,876 | - |
$8,876
207,831
kWh
|
- | - | - | - | - | |
09 | 2.2621: Modify refrigeration system to operate at a lower pressure | $2,533 | $2,000 |
$2,533
59,296
kWh
|
- | - | - | - | - | |
10 | 2.6231: Utilize controls to operate equipment only when needed | $2,365 | $11,824 |
$2,365
55,370
kWh
|
- | - | - | - | - | |
11 | 2.2626: Avoid frost formation on evaporators | $1,417 | - |
$1,417
33,178
kWh
|
- | - | - | - | - | |
12 | 2.2621: Modify refrigeration system to operate at a lower pressure | $1,101 | - |
$1,101
25,772
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $58,045 | $61,174 |
$32,249
755,074
kWh
|
$4,241
-
kW-mo/yr
|
$9,148 |
$12,434
-
MMBtu
|
$573 | $(-600.0) | ||
TOTAL IMPLEMENTED | $58,045 | $61,174 |
$32,249
755,074
kWh
|
$4,241
-
kW-mo/yr
|
$9,148 |
$12,434
-
MMBtu
|
$573 | $(-600.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs