ITAC Assessment: WI0235
ITAC logo
ITAC Assessment: WI0235
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Teflon Coated Fabric
NAICS
n/a
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 24,700
ft2
Annual Production 3,000,000
thousand feet
Production Hrs. Annual 4,800
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $81,066 1,215,416
kWh
Natural Gas $129,188 43,990
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,844 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,074 $13,000 $5,074
146,249
kWh
- - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,822 - $4,822
-
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,337 $1,864 $1,337
19,930
kWh
- - -
04 2.7111: Reduce illumination to minimum necessary levels $884 - $884
13,189
kWh
- - -
05 2.7135: Install occupancy sensors $388 $750 $388
5,862
kWh
- - -
06 2.7221: Lower temperature during the winter season and vice-versa $1,145 $200 - $1,145
-
MMBtu
- -
07 2.2511: Insulate bare equipment $505 $50 $505
7,620
kWh
- - -
08 2.7447: Install vinyl strip / high speed / air curtain doors $368 $875 - $368
-
MMBtu
- -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $121 - $121
1,758
kWh
- - -
10 3.6193: Install equipment (eg compactor) to reduce disposal costs $4,200 - $(-100.0)
(-1,172)
kWh
- $5,300
-
lb
$(-1,000.0)
TOTAL RECOMMENDED $18,844 $16,739 $13,031
193,436
kWh
$1,513
-
MMBtu
$5,300
-
lb
$(-1,000.0)
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs