| Assessment Year | 1995 |
|---|---|
| Principal Product | Teflon Coated Fabric |
| NAICS |
n/a
|
| SIC | 2295: Coated Fabrics, Not Rubberized |
| Sales Range | $10 M to 50M |
| # of Employees | 55 |
| Plant Area |
24,700
ft2
|
| Annual Production | 3,000,000
thousand feet
|
| Production Hrs. Annual | 4,800
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $81,066 | 1,215,416 |
kWh
|
$0.067 |
| Natural Gas | $129,188 | 43,990 |
MMBtu
|
$2.94 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,844 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,074 | $13,000 |
$5,074
146,249
kWh
|
- | - | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,822 | - |
$4,822
-
kWh
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,337 | $1,864 |
$1,337
19,930
kWh
|
- | - | - | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $884 | - |
$884
13,189
kWh
|
- | - | - | |
| 05 | 2.7135: Install occupancy sensors | $388 | $750 |
$388
5,862
kWh
|
- | - | - | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $1,145 | $200 | - |
$1,145
-
MMBtu
|
- | - | |
| 07 | 2.2511: Insulate bare equipment | $505 | $50 |
$505
7,620
kWh
|
- | - | - | |
| 08 | 2.7447: Install vinyl strip / high speed / air curtain doors | $368 | $875 | - |
$368
-
MMBtu
|
- | - | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $121 | - |
$121
1,758
kWh
|
- | - | - | |
| 10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,200 | - |
$(-100.0)
(-1,172)
kWh
|
- |
$5,300
-
lb
|
$(-1,000.0) | |
| TOTAL RECOMMENDED | $18,844 | $16,739 |
$13,031
193,436
kWh
|
$1,513
-
MMBtu
|
$5,300
-
lb
|
$(-1,000.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs