| Assessment Year | 1995 |
|---|---|
| Principal Product | Bread, buns & rolls |
| NAICS |
n/a
|
| SIC | 2051: Bread and Other Bakery Products, Except Cookies and Crackers |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
175,000
ft2
|
| Annual Production | 18,000,000
lb
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $114,796 | 2,173,212 |
kWh
|
$0.053 |
| Natural Gas | $140,867 | 47,070 |
MMBtu
|
$2.99 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,571 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,187 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,847 | $8,000 |
$5,847
-
kWh
|
- | - | - | |
| 02 | 2.2621: Modify refrigeration system to operate at a lower pressure | $5,652 | $12,000 |
$5,652
106,975
kWh
|
- | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,790 | $500 | - |
$3,790
-
MMBtu
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,066 | $1,860 |
$2,066
39,273
kWh
|
- | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $550 | - |
$550
10,551
kWh
|
- | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $196 | - |
$196
3,810
kWh
|
- | - | - | |
| 07 | 2.2612: Use cooling tower water instead of refrigeration | $5,470 | $12,000 | - | - |
$5,470
-
Tgal
|
- | |
| 08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,000 | - | - | - | - |
$5,000
-
lb
|
|
| TOTAL RECOMMENDED | $28,571 | $34,360 |
$14,311
160,609
kWh
|
$3,790
-
MMBtu
|
$5,470
-
Tgal
|
$5,000
-
lb
|
||
| TOTAL IMPLEMENTED | $15,187 | $8,500 |
$6,397
10,551
kWh
|
$3,790
-
MMBtu
|
- |
$5,000
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs