ITAC Assessment: WI0223
ITAC logo
ITAC Assessment: WI0223
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Books and Brochures
NAICS
n/a
SIC 2731: Books: Publishing, or Publishing and Printing
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 80,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,403 728,898
kWh
Natural Gas $28,389 5,824
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,394 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,726

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1224: Replace boiler $3,696 $6,500 - $3,696
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,412 $2,989 $2,412
33,705
kWh
-
03 2.7135: Install occupancy sensors $228 $225 $228
3,224
kWh
-
04 2.3135: Schedule routine maintenance during non-operating periods $1,910 - $1,910
-
kWh
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $816 - $816
-
kWh
-
06 2.4221: Install compressor air intakes in coolest locations $332 $640 $332
4,396
kWh
-
TOTAL RECOMMENDED $9,394 $10,354 $5,698
41,325
kWh
$3,696
-
MMBtu
TOTAL IMPLEMENTED $2,726 - $2,726
-
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs