| Assessment Year | 2001 |
|---|---|
| Principal Product | Cement and Mining Equiment |
| NAICS |
n/a
|
| SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
170,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $245,670 | 3,411,000 |
kWh
|
$0.072 |
| Electricity Demand | $47,805 | 683 |
kW-mo/yr
|
$69.99 |
| Fuel Oil #4 | $182,260 | 30,630 |
MMBtu
|
$5.95 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,729 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,166 | $2,500 | - |
$7,166
-
kW-mo/yr
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,785 | - |
$2,152
41,397
kWh
|
$633
-
kW-mo/yr
|
- | |
| 03 | 2.4312: Improve lubrication practices | $2,615 | $400 |
$2,615
50,282
kWh
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $11,513 | $25,360 | - | - |
$11,513
-
MMBtu
|
|
| 05 | 2.2111: Install steam trap | $1,315 | $1,600 | - | - |
$1,315
-
MMBtu
|
|
| 06 | 2.2514: Cover open tanks | $5,335 | $1,700 | - | - |
$5,335
-
MMBtu
|
|
| TOTAL RECOMMENDED | $30,729 | $31,560 |
$4,767
91,679
kWh
|
$7,799
-
kW-mo/yr
|
$18,163
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #4 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs