| Assessment Year | 1994 |
|---|---|
| Principal Product | Metal,Polyester, & Plastic zippers, fabricated buckled/unbuc |
| NAICS |
n/a
|
| SIC | 3965: Fasteners, Buttons, Needles, and Pins |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
59,400
ft2
|
| Annual Production | 24,000,000
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $57,371 | 738,863 |
kWh
|
$0.078 |
| Natural Gas | $14,433 | 3,484 |
MMBtu
|
$4.14 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,020 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,665 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3135: Schedule routine maintenance during non-operating periods | $4,449 | - | - |
$4,449
-
MMBtu
|
|
| 02 | 2.7224: Reduce space conditioning during non-working hours | $4,383 | $2,000 | - |
$4,383
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,758 | $4,000 |
$2,758
35,463
kWh
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $669 | $1,713 |
$669
8,499
kWh
|
- | |
| 05 | 2.7135: Install occupancy sensors | $663 | $600 |
$663
8,499
kWh
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,597 | $1,000 |
$1,597
23,740
kWh
|
- | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $501 | $640 |
$501
6,448
kWh
|
- | |
| TOTAL RECOMMENDED | $15,020 | $9,953 |
$6,188
82,649
kWh
|
$8,832
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $10,665 | $4,953 |
$1,833
23,446
kWh
|
$8,832
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs