ITAC Assessment: WI0208
ITAC logo
ITAC Assessment: WI0208
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Series universal motors of fractional horsepower for vacuum
NAICS
n/a
SIC 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment
Sales Range $10
M
to 50
M
# of Employees 600
Plant Area 210,000
ft2
Annual Production 4,200,000
pieces
Production Hrs. Annual 6,600
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $417,574 8,369,578
kWh
Natural Gas $81,888 16,527
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,375 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,158

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $20,158 - - - - $20,158
02 2.2612: Use cooling tower water instead of refrigeration $8,821 $15,000 $8,821
-
kWh
- - -
03 2.3132: Recharge batteries on during off-peak demand periods $7,036 $20,412 $7,036
-
kWh
- - -
04 2.6231: Utilize controls to operate equipment only when needed $5,198 $12,000 $5,198
104,338
kWh
- - -
05 2.2511: Insulate bare equipment $335 $329 - $335
-
MMBtu
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $327 $820 $327
6,448
kWh
- - -
07 3.8142: Distill contaminated solvents for reuse $5,500 $12,000 - - $5,500
-
Tgal
-
TOTAL RECOMMENDED $47,375 $60,561 $21,382
110,786
kWh
$335
-
MMBtu
$5,500
-
Tgal
$20,158
TOTAL IMPLEMENTED $20,158 - - - - $20,158
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs