ITAC Assessment: WI0201
ITAC logo
ITAC Assessment: WI0201
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Electrical contractors
NAICS
n/a
SIC 3537: Industrial Trucks, Tractors, Trailers, and Stackers
Sales Range $5
M
to 10
M
# of Employees 213
Plant Area 125,952
ft2
Annual Production 0
units
Production Hrs. Annual 3,500
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,558 1,417,937
kWh
Natural Gas $20,008 4,574
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,034 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,748

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2612: Use cooling tower water instead of refrigeration $12,890 $42,825 $12,890
236,225
kWh
- -
02 2.7241: Install outside air damper / economizer on hvac unit $1,873 $2,800 $1,873
25,791
kWh
- -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $8,555 $20,000 $11,492
157,386
kWh
$(-2,937.0)
-
MMBtu
-
04 2.6218: Turn off equipment when not in use $4,040 $800 $4,040
55,393
kWh
- -
05 2.2511: Insulate bare equipment $287 $142 $287
3,810
kWh
- -
06 2.7224: Reduce space conditioning during non-working hours $2,906 $800 - $2,906
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,915 $6,824 $2,915
39,859
kWh
- -
08 2.7135: Install occupancy sensors $470 $375 $470
6,448
kWh
- -
09 2.3132: Recharge batteries on during off-peak demand periods $2,847 - $2,847
-
kWh
- -
10 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,643 - - - $1,643
11 2.7447: Install vinyl strip / high speed / air curtain doors $437 $1,023 - $437
-
MMBtu
-
12 2.4221: Install compressor air intakes in coolest locations $171 $640 $171
2,345
kWh
- -
TOTAL RECOMMENDED $39,034 $76,229 $36,985
527,257
kWh
$406
-
MMBtu
$1,643
TOTAL IMPLEMENTED $10,748 $8,647 $5,762
39,859
kWh
$3,343
-
MMBtu
$1,643
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs