ITAC Assessment: WI0197
ITAC logo
ITAC Assessment: WI0197
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Powered Metal Parts
NAICS
n/a
SIC 3441: Fabricated Structural Metal
Sales Range $5
M
to 10
M
# of Employees 130
Plant Area 46,000
ft2
Annual Production 10,800,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $176,690 4,113,716
kWh
Natural Gas $80,595 16,976
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,610 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $55,055

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4321: Upgrade obsolete equipment $16,304 $30,000 $16,304
379,836
kWh
- -
02 2.8113: Purchase gas directly from a contract gas supplier $33,894 $500 - - $33,894
03 2.2511: Insulate bare equipment $6,277 $1,167 $6,277
167,644
kWh
- -
04 2.7224: Reduce space conditioning during non-working hours $1,426 $200 - $1,426
-
MMBtu
-
05 2.4221: Install compressor air intakes in coolest locations $3,431 $960 $3,431
80,012
kWh
- -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,900 $2,741 $1,900
44,256
kWh
- -
07 2.7135: Install occupancy sensors $807 $525 $807
18,757
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $167 $300 $167
3,810
kWh
- -
09 2.3132: Recharge batteries on during off-peak demand periods $404 - $404
-
kWh
- -
TOTAL RECOMMENDED $64,610 $36,393 $29,290
694,315
kWh
$1,426
-
MMBtu
$33,894
TOTAL IMPLEMENTED $55,055 $31,660 $19,735
459,848
kWh
$1,426
-
MMBtu
$33,894
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs