ITAC Assessment: WI0158
ITAC logo
ITAC Assessment: WI0158
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PUMPS
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 25,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $111,755 1,744,138
kWh
Natural Gas $49,431 10,816
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,372 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,199

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,381 - $5,881
-
kWh
- $(-1,500.0)
02 2.8121: Apply for tax-free status for energy purchases $4,154 - $3,926
-
kWh
$228
-
MMBtu
-
03 2.3212: Optimize plant power factor $3,161 $8,000 $3,161
-
kWh
- -
04 2.7111: Reduce illumination to minimum necessary levels $5,382 - $5,382
84,115
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $663 $2,555 $781
12,309
kWh
- $(-118.0)
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,099 $1,400 $1,579
24,619
kWh
$(-480.0)
-
MMBtu
-
07 2.4221: Install compressor air intakes in coolest locations $532 $1,800 $532
8,206
kWh
- -
TOTAL RECOMMENDED $19,372 $13,755 $21,242
129,249
kWh
$(-252.0)
-
MMBtu
$(-1,618.0)
TOTAL IMPLEMENTED $10,199 $2,555 $10,089
96,424
kWh
$228
-
MMBtu
$(-118.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs