Assessment Year | 1992 |
---|---|
Principal Product | PRINTING/BINDING BOOKS |
NAICS |
n/a
|
SIC | 2731: Books: Publishing, or Publishing and Printing |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
n/a
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $252,157 | 3,128,077 |
kWh
|
$0.081 |
Fuel Oil #2 | $50,726 | 9,015 |
MMBtu
|
$5.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,152 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,601 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,838 | $3,915 |
$6,838
84,994
kWh
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,003 | - |
$1,003
12,603
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,382 | $7 |
$3,863
47,773
kWh
|
- | $(-481.0) | |
04 | 2.3132: Recharge batteries on during off-peak demand periods | $2,601 | - |
$2,601
-
kWh
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $1,537 | $1,300 | - |
$1,537
-
MMBtu
|
- | |
06 | 2.4221: Install compressor air intakes in coolest locations | $600 | $640 |
$600
7,327
kWh
|
- | - | |
07 | 2.2511: Insulate bare equipment | $191 | $178 |
$191
2,345
kWh
|
- | - | |
TOTAL RECOMMENDED | $16,152 | $6,040 |
$15,096
155,042
kWh
|
$1,537
-
MMBtu
|
$(-481.0) | ||
TOTAL IMPLEMENTED | $2,601 | - |
$2,601
-
kWh
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs