ITAC Assessment: WI0080
ITAC logo
ITAC Assessment: WI0080
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product ENVELOPES & LETTERHEAD
NAICS
n/a
SIC 2759: Commercial Printing, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area
n/a
Annual Production 3,500,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $292,082 3,882,474
kWh
Natural Gas $76,150 14,017
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,121 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,322

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $32,758 - - $32,758
-
MMBtu
-
02 2.2414: Use waste heat from hot flue gases to preheat $7,722 $10,000 - $7,722
-
MMBtu
-
03 2.6218: Turn off equipment when not in use $1,752 $1,600 - $1,752
-
MMBtu
-
04 2.7494: Install storm windows and doors $1,672 $2,640 - $1,672
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,274 $500 - $1,474
-
MMBtu
$(-200.0)
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,098 - $1,098
14,654
kWh
- -
07 2.3132: Recharge batteries on during off-peak demand periods $520 $1,250 $520
-
kWh
- -
08 2.6232: Install set-back timers $325 $400 $325
4,396
kWh
- -
TOTAL RECOMMENDED $47,121 $16,390 $1,943
19,050
kWh
$45,378
-
MMBtu
$(-200.0)
TOTAL IMPLEMENTED $37,322 $4,390 $1,618
14,654
kWh
$35,904
-
MMBtu
$(-200.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs