| Assessment Year | 1989 |
|---|---|
| Principal Product | ICE CREAM TOPPINGS |
| NAICS |
n/a
|
| SIC | 2066: Chocolate and Cocoa Products |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
n/a
|
| Annual Production | 62,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $356,134 | 7,857,562 |
kWh
|
$0.045 |
| Natural Gas | $199,102 | 50,961 |
MMBtu
|
$3.91 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $79,877 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $78,849 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $40,435 | - | - |
$40,435
-
MMBtu
|
- | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $14,520 | - |
$16,920
-
kWh
|
- | $(-2,400.0) | |
| 03 | 2.4312: Improve lubrication practices | $8,793 | $713 |
$8,793
199,590
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,476 | $8,464 |
$1,476
33,411
kWh
|
- | - | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $5,852 | $7,000 | - |
$5,852
-
MMBtu
|
- | |
| 06 | 2.3132: Recharge batteries on during off-peak demand periods | $4,976 | - |
$4,976
-
kWh
|
- | - | |
| 07 | 2.7494: Install storm windows and doors | $1,472 | $2,444 | - |
$1,472
-
MMBtu
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,325 | - |
$1,325
30,188
kWh
|
- | - | |
| 09 | 2.4221: Install compressor air intakes in coolest locations | $1,028 | $3,000 |
$1,028
23,447
kWh
|
- | - | |
| TOTAL RECOMMENDED | $79,877 | $21,621 |
$34,518
286,636
kWh
|
$47,759
-
MMBtu
|
$(-2,400.0) | ||
| TOTAL IMPLEMENTED | $78,849 | $18,621 |
$33,490
263,189
kWh
|
$47,759
-
MMBtu
|
$(-2,400.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs