Assessment Year | 1989 |
---|---|
Principal Product | ROLLERS |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $115,108 | 1,859,027 |
kWh
|
$0.062 |
Natural Gas | $39,017 | 9,174 |
MMBtu
|
$4.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,864 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,028 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $3,210 | $500 |
$3,210
51,876
kWh
|
- | - | |
02 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $3,901 | $1,300 |
$3,080
49,824
kWh
|
$821
-
MMBtu
|
- | |
03 | 2.3132: Recharge batteries on during off-peak demand periods | $238 | - |
$238
-
kWh
|
- | - | |
04 | 2.3134: Shift from daytime to nighttime operation | $1,836 | - |
$2,436
-
kWh
|
- | $(-600.0) | |
05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $9,913 | $3,600 |
$11,001
60,082
kWh
|
$(-1,088.0)
-
MMBtu
|
- | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,766 | $2,100 | - |
$1,766
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $20,864 | $7,500 |
$19,965
161,782
kWh
|
$1,499
-
MMBtu
|
$(-600.0) | ||
TOTAL IMPLEMENTED | $19,028 | $7,500 |
$17,529
161,782
kWh
|
$1,499
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs