ITAC Assessment: WI0047
ITAC logo
ITAC Assessment: WI0047
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product ROLLERS
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $115,108 1,859,027
kWh
Natural Gas $39,017 9,174
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,864 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,028

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $3,210 $500 $3,210
51,876
kWh
- -
02 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $3,901 $1,300 $3,080
49,824
kWh
$821
-
MMBtu
-
03 2.3132: Recharge batteries on during off-peak demand periods $238 - $238
-
kWh
- -
04 2.3134: Shift from daytime to nighttime operation $1,836 - $2,436
-
kWh
- $(-600.0)
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $9,913 $3,600 $11,001
60,082
kWh
$(-1,088.0)
-
MMBtu
-
06 2.7447: Install vinyl strip / high speed / air curtain doors $1,766 $2,100 - $1,766
-
MMBtu
-
TOTAL RECOMMENDED $20,864 $7,500 $19,965
161,782
kWh
$1,499
-
MMBtu
$(-600.0)
TOTAL IMPLEMENTED $19,028 $7,500 $17,529
161,782
kWh
$1,499
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs