| Assessment Year | 2026 |
|---|---|
| Principal Product | Plastic Cutlery |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 180 |
| Plant Area |
76,265
ft2
|
| Annual Production | 4,400,000,000
pieces
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,152,395 | 14,518,363 |
kWh
|
$0.079 |
| Electricity Demand | $317,905 | 21,821 |
kW-mo/yr
|
$14.57 |
| TOTAL YEARLY COSTS | $1,470,300 | |||
| RECOMMENDED SAVINGS* | $336,719 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $14,331 | $5,600 |
$8,939
112,615
kWh
|
$5,392
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,988 | $2,140 |
$3,988
50,233
kWh
|
- | - | |
| 03 | 2.4322: Use or replace with energy efficient substitutes | $7,046 | $40,000 |
$5,629
71,000
kWh
|
$1,417
-
kW-mo/yr
|
- | |
| 04 | 2.9114: Use solar heat to make electricty | $202,661 | $2,468,607 |
$202,661
1,616,000
kWh
|
- | - | |
| 05 | 2.4322: Use or replace with energy efficient substitutes | $8,693 | $58,000 |
$6,947
87,512
kWh
|
$1,746
-
kW-mo/yr
|
- | |
| 06 | 3.2176: Increase use of automation | $100,000 | $403,150 | - | - | $100,000 | |
| TOTAL RECOMMENDED | $336,719 | $2,977,497 |
$228,164
1,937,360
kWh
|
$8,555
-
kW-mo/yr
|
$100,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs