ITAC Assessment: WI0042
ITAC logo
ITAC Assessment: WI0042
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product RELAYS, SOLENOIDS
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 260
Plant Area
n/a
Annual Production 3,800,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $186,258 3,769,930
kWh
Natural Gas $32,993 6,974
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,082

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4312: Improve lubrication practices $5,488 - $5,488
111,079
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $624 - $624
12,603
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,829 $309 $1,829
36,928
kWh
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,254 $1,650 $2,114
42,790
kWh
$(-860.0)
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $356 $500 $356
7,327
kWh
-
06 2.3132: Recharge batteries on during off-peak demand periods $446 - $446
-
kWh
-
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,012 $250 $3,012
60,961
kWh
-
TOTAL RECOMMENDED $13,009 $2,709 $13,869
271,688
kWh
$(-860.0)
-
MMBtu
TOTAL IMPLEMENTED $4,082 $250 $4,082
73,564
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs