ITAC Assessment: WI0039
ITAC logo
ITAC Assessment: WI0039
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product LABEL MACHINES & PARTS
NAICS
n/a
SIC 3554: Paper Industries Machinery
Sales Range $5
M
to 10
M
# of Employees 113
Plant Area
n/a
Annual Production 20
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,039 936,987
kWh
Natural Gas $26,463 5,555
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,723 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,982

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4312: Improve lubrication practices $5,741 - $5,741
97,890
kWh
-
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,762 - $1,762
29,894
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,771 $514 $2,771
46,893
kWh
-
04 2.7447: Install vinyl strip / high speed / air curtain doors $2,175 $1,400 - $2,175
-
MMBtu
05 2.6214: Shut off pilots in standby equipment $274 - - $274
-
MMBtu
TOTAL RECOMMENDED $12,723 $1,914 $10,274
174,677
kWh
$2,449
-
MMBtu
TOTAL IMPLEMENTED $6,982 $1,914 $4,533
76,787
kWh
$2,449
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs