ITAC Assessment: BS0081
ITAC logo
ITAC Assessment: BS0081
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Dimensional Lumber
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $50
M
to 100
M
# of Employees 72
Plant Area 85,000
ft2
Annual Production 65,000
thousand feet
Production Hrs. Annual 4,680
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $280,439 4,584,685
kWh
Electricity Demand $64,839 11,588
kW-mo/yr
Wood $259,584 124,800
MMBtu
TOTAL YEARLY COSTS $604,862
RECOMMENDED SAVINGS* $22,249 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,261

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,089 $4,550 $6,031
98,548
kWh
$1,058
-
kW-mo/yr
-
02 2.6212: Turn off equipment during breaks, reduce operating time $10,309 $150 $10,309
169,005
kWh
- -
03 2.2122: Install / repair insulation on condensate lines $72 $311 - - $72
-
MMBtu
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,916 $80 $3,205
52,364
kWh
$711
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $462 $15 $308
5,037
kWh
$154
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $401 $550 $401
6,570
kWh
- -
TOTAL RECOMMENDED $22,249 $5,656 $20,254
331,524
kWh
$1,923
-
kW-mo/yr
$72
-
MMBtu
TOTAL IMPLEMENTED $18,261 $5,265 $17,049
279,160
kWh
$1,212
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs