ITAC Assessment: WI0036
ITAC logo
ITAC Assessment: WI0036
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product HYDRAULIC CYLINDERS
NAICS
n/a
SIC 3593: Fluid Power Cylinders and Actuators
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area
n/a
Annual Production 6,000
pieces
Production Hrs. Annual 4,675
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $120,395 1,890,973
kWh
Natural Gas $33,512 6,468
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,186 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,615

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $4,529 - $4,529
71,219
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,402 - $1,402
21,981
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $793 $234 $793
12,603
kWh
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $824 $500 - $1,124
-
MMBtu
$(-300.0)
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $751 $1,300 $1,150
18,171
kWh
$(-399.0)
-
MMBtu
-
06 2.3191: Use demand controller or load shedder $2,820 $5,000 $2,820
-
kWh
- -
07 2.3132: Recharge batteries on during off-peak demand periods $4,459 - $4,459
-
kWh
- -
08 2.7447: Install vinyl strip / high speed / air curtain doors $4,608 $5,500 - $4,808
-
MMBtu
$(-200.0)
TOTAL RECOMMENDED $20,186 $12,534 $15,153
123,974
kWh
$5,533
-
MMBtu
$(-500.0)
TOTAL IMPLEMENTED $16,615 $6,234 $11,183
105,803
kWh
$5,932
-
MMBtu
$(-500.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs