| Assessment Year | 1988 |
|---|---|
| Principal Product | SAND CAST TRANSMISSION |
| NAICS |
n/a
|
| SIC | 3365: Aluminum Foundries |
| Sales Range | $1 M to 5M |
| # of Employees | 65 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $89,413 | 1,105,803 |
kWh
|
$0.081 |
| Natural Gas | $74,990 | 15,221 |
MMBtu
|
$4.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $36,041 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,092 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4312: Improve lubrication practices | $7,240 | - |
$7,240
89,683
kWh
|
- | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,253 | - |
$2,253
27,843
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $33 | $563 |
$33
293
kWh
|
- | |
| 04 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,819 | $1,400 | - |
$1,819
-
MMBtu
|
|
| 05 | 2.7226: Use computer programs to optimize hvac performance | $1,026 | $2,500 |
$1,026
12,603
kWh
|
- | |
| 06 | 2.8113: Purchase gas directly from a contract gas supplier | $23,670 | - | - |
$23,670
-
MMBtu
|
|
| TOTAL RECOMMENDED | $36,041 | $4,463 |
$10,552
130,422
kWh
|
$25,489
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,092 | $1,963 |
$7,273
89,976
kWh
|
$1,819
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs