ITAC Assessment: WI0011
ITAC logo
ITAC Assessment: WI0011
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product SHAPED WIRE
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area
n/a
Annual Production 40,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $302,425 5,788,101
kWh
Natural Gas $48,513 9,795
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,783 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,108

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $23,501 - $23,501
449,883
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $13,151 - $13,151
251,759
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,974 $4,177 $5,974
114,302
kWh
- -
04 2.6121: Reduce hot water temperature to the minimum required $265 - $265
-
kWh
- -
05 2.1233: Analyze flue gas for proper air/fuel ratio $983 $500 - $1,083
-
MMBtu
$(-100.0)
06 2.7447: Install vinyl strip / high speed / air curtain doors $1,909 $750 - $1,909
-
MMBtu
-
TOTAL RECOMMENDED $45,783 $5,427 $42,891
815,944
kWh
$2,992
-
MMBtu
$(-100.0)
TOTAL IMPLEMENTED $20,108 $4,677 $19,125
366,061
kWh
$1,083
-
MMBtu
$(-100.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs