| Assessment Year | 2011 |
|---|---|
| Principal Product | cat litter |
| NAICS | 327992: Ground or Treated Mineral and Earth Manufacturing |
| SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
| Sales Range | $10 M to 50M |
| # of Employees | 40 |
| Plant Area |
1,225,391
ft2
|
| Annual Production | 100,000
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $457,435 | 5,912,100 |
kWh
|
$0.077 |
| Electricity Demand | $80,596 | 12,537 |
kW-mo/yr
|
$6.43 |
| Natural Gas | $309,002 | 194,482 |
MMBtu
|
$1.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $98,768 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $12,701 | $6,982 | - | - |
$12,701
-
MMBtu
|
|
| 02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $455 | $985 | - | - |
$455
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,292 | $12,615 |
$19,705
252,626
kWh
|
$3,587
-
kW-mo/yr
|
- | |
| 04 | 2.7134: Use photocell controls | $439 | $147 |
$439
5,634
kWh
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $125 | $120 |
$125
1,594
kWh
|
- | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $18,042 | - |
$18,042
196,675
kWh
|
- | - | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,286 | $680 |
$19,753
256,532
kWh
|
$4,533
-
kW-mo/yr
|
- | |
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,428 | $19,015 |
$15,801
205,209
kWh
|
$3,627
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $98,768 | $40,544 |
$73,865
918,270
kWh
|
$11,747
-
kW-mo/yr
|
$13,156
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs