ITAC Assessment: WI0006
ITAC logo
ITAC Assessment: WI0006
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product LEATHER
NAICS
n/a
SIC 3111: Leather Tanning and Finishing
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area
n/a
Annual Production 5,000
thousand feet
Production Hrs. Annual 3,000
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,134 1,762,016
kWh
Natural Gas $150,254 38,242
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,937 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,199

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $5,243 - $5,243
73,857
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,121 - $2,121
29,894
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $958 $1,529 $958
13,482
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $495 $561 $495
7,034
kWh
- -
05 2.3191: Use demand controller or load shedder $1,988 - $1,988
-
kWh
- -
06 2.1233: Analyze flue gas for proper air/fuel ratio $3,132 - - $3,382
-
MMBtu
$(-250.0)
TOTAL RECOMMENDED $13,937 $2,090 $10,805
124,267
kWh
$3,382
-
MMBtu
$(-250.0)
TOTAL IMPLEMENTED $8,199 $1,529 $5,067
43,376
kWh
$3,382
-
MMBtu
$(-250.0)