ITAC Assessment: UW2512
ITAC logo
ITAC Assessment: UW2512
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product vaccines
NAICS 325414: Biological Product (except Diagnostic) Manufacturing
SIC 2836: Biological Products, Except Diagnostic Substances
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 52,500
ft2
Annual Production 150,000,000
pieces
Production Hrs. Annual 5,902
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $198,437 2,067,200
kWh
Electricity Demand $68,497 4,390
kW-mo/yr
Natural Gas $50,700 3,651
MMBtu
TOTAL YEARLY COSTS $317,634
RECOMMENDED SAVINGS* $60,453 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4221: Install compressor air intakes in coolest locations $784 $2,121 $589
6,135
kWh
$195
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $23,750 $33,267 $21,710
226,153
kWh
$2,040
-
kW-mo/yr
03 2.7135: Install occupancy sensors $35,919 $16,149 $35,919
374,158
kWh
-
TOTAL RECOMMENDED $60,453 $51,536 $58,218
606,446
kWh
$2,235
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs