Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Aluminum, steel, titanium, uncured rubber
NAICS 336411: Aircraft Manufacturing
SIC 3721: Aircraft
Sales Range $10
M
to 50
M
# of Employees 52
Plant Area 80,600
ft2
Annual Production 3,640
pieces
Production Hrs. Annual 4,680
hrs
Location (State) Alaska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $42,441 460,800
kWh
Electricity Demand $26,107 3,139
kW-mo/yr
Electricity Fees $35,065 -
Natural Gas $27,067 2,169
MMBtu
TOTAL YEARLY COSTS $130,680
RECOMMENDED SAVINGS* $116,663 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,224 $25,000 $6,430
69,817
kWh
$794
-
kW-mo/yr
- - -
02 4.515: Install shelves / racks to utilize unused space $28,715 $117,000 - - - $28,715 -
03 2.2628: Utilize a less expensive cooling method $14,693 $183,000 $2,522
27,384
kWh
$171
-
kW-mo/yr
- - $12,000
04 4.721: Initiate a program to acquire iso certification $11,474 $47,500 $5,093
55,296
kWh
$3,133
-
kW-mo/yr
$3,248
-
MMBtu
- -
05 2.9114: Use solar heat to make electricty $54,557 $477,475 $54,557
592,369
kWh
- - - -
TOTAL RECOMMENDED $116,663 $849,975 $68,602
744,866
kWh
$4,098
-
kW-mo/yr
$3,248
-
MMBtu
$28,715 $12,000
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs