Assessment Year | 2024 |
---|---|
Principal Product | Aluminum, steel, titanium, uncured rubber |
NAICS | 336411: Aircraft Manufacturing |
SIC | 3721: Aircraft |
Sales Range | $10 M to 50M |
# of Employees | 52 |
Plant Area |
80,600
ft2
|
Annual Production | 3,640
pieces
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Alaska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $42,441 | 460,800 |
kWh
|
$0.092 |
Electricity Demand | $26,107 | 3,139 |
kW-mo/yr
|
$8.32 |
Electricity Fees | $35,065 | - |
|
- |
Natural Gas | $27,067 | 2,169 |
MMBtu
|
$12.48 |
TOTAL YEARLY COSTS | $130,680 | |||
RECOMMENDED SAVINGS* | $116,663 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,224 | $25,000 |
$6,430
69,817
kWh
|
$794
-
kW-mo/yr
|
- | - | - | |
02 | 4.515: Install shelves / racks to utilize unused space | $28,715 | $117,000 | - | - | - | $28,715 | - | |
03 | 2.2628: Utilize a less expensive cooling method | $14,693 | $183,000 |
$2,522
27,384
kWh
|
$171
-
kW-mo/yr
|
- | - | $12,000 | |
04 | 4.721: Initiate a program to acquire iso certification | $11,474 | $47,500 |
$5,093
55,296
kWh
|
$3,133
-
kW-mo/yr
|
$3,248
-
MMBtu
|
- | - | |
05 | 2.9114: Use solar heat to make electricty | $54,557 | $477,475 |
$54,557
592,369
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $116,663 | $849,975 |
$68,602
744,866
kWh
|
$4,098
-
kW-mo/yr
|
$3,248
-
MMBtu
|
$28,715 | $12,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs