Assessment Year | 2024 |
---|---|
Principal Product | Solide stile and rail wood doors |
NAICS | 321911: Wood Window and Door Manufacturing |
SIC | 2431: Millwork |
Sales Range | $50 M to 100M |
# of Employees | 216 |
Plant Area |
356,760
ft2
|
Annual Production | 70,000
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $617,253 | 10,079,000 |
kWh
|
$0.061 | |
Electricity Demand | $284,955 | 36,900 |
kW-mo/yr
|
$7.72 | |
Electricity Fees | $89,227 | - |
|
- | |
LPG | $227,211 | 14,726 |
MMBtu
|
$15.43 | |
Waste Disposal Costs | |||||
Water Usage | $3,192 | 53,855 |
Tgal
|
$0.059 | |
Water Disposal | $52,330 | 53,855 |
Tgal
|
$0.97 | |
TOTAL YEARLY COSTS | $1,274,168 | ||||
RECOMMENDED SAVINGS* | $495,245 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7447: Install vinyl strip / high speed / air curtain doors | $13,069 | $103,000 | - | - | - |
$13,069
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $116,105 | $13,500 | - | - | - |
$116,105
-
MMBtu
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,014 | - |
$5,277
86,226
kWh
|
$2,737
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $32,306 | $2,080 |
$26,082
426,174
kWh
|
$6,224
-
kW-mo/yr
|
- | - | |
05 | 2.3212: Optimize plant power factor | $45,697 | $89,919 | - |
$26,778
-
kW-mo/yr
|
$18,919 | - | |
06 | 2.7313: Recycle air for heating, ventilation and air conditioning | $35,732 | $2,619 |
$35,732
583,858
kWh
|
- | - | - | |
07 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $34,834 | $133,560 |
$34,834
569,176
kWh
|
- | - | - | |
08 | 2.2123: Insulate feedwater tank | $2,901 | $290 | - | - | - |
$2,901
-
MMBtu
|
|
09 | 2.9114: Use solar heat to make electricty | $61,411 | $421,830 |
$52,361
855,564
kWh
|
$9,050
-
kW-mo/yr
|
- | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $145,176 | $144,799 |
$84,015
1,372,800
kWh
|
$61,161
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $495,245 | $911,597 |
$238,301
3,893,798
kWh
|
$105,950
-
kW-mo/yr
|
$18,919 |
$132,075
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs