Assessment Year | 2024 |
---|---|
Principal Product | Other Aircraft Parts and Auxiliary Equipment Manufacturing |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 131 |
Plant Area |
61,000
ft2
|
Annual Production | 950,000
units
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $300,101 | 4,322,533 |
kWh
|
$0.069 |
Electricity Demand | $51,855 | 8,466 |
kW-mo/yr
|
$6.13 |
Electricity Fees | $18,013 | - |
|
- |
Natural Gas | $636,069 | 96,856 |
MMBtu
|
$6.57 |
TOTAL YEARLY COSTS | $1,006,038 | |||
RECOMMENDED SAVINGS* | $184,395 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $184,395 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 4.662: Level one – add communication using iiot devices to existing control system to modify operations | $141,044 | $149,500 |
$44,998
648,380
kWh
|
- |
$96,046
-
MMBtu
|
|
02 | 2.4221: Install compressor air intakes in coolest locations | $1,688 | $3,000 |
$1,502
21,638
kWh
|
$186
-
kW-mo/yr
|
- | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $1,711 | $4,441 |
$(-1,384.0)
(-19,940)
kWh
|
$(-436.0)
-
kW-mo/yr
|
$3,531
-
MMBtu
|
|
04 | 2.3212: Optimize plant power factor | $6,204 | $23,347 | - |
$6,204
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,098 | $26,080 |
$6,317
91,035
kWh
|
$781
-
kW-mo/yr
|
- | |
06 | 2.2136: Install / repair insulation on steam lines | $26,650 | $58,013 | - | - |
$26,650
-
MMBtu
|
|
TOTAL RECOMMENDED | $184,395 | $264,381 |
$51,433
741,113
kWh
|
$6,735
-
kW-mo/yr
|
$126,227
-
MMBtu
|
||
TOTAL IMPLEMENTED | $184,395 | $264,381 |
$51,433
741,113
kWh
|
$6,735
-
kW-mo/yr
|
$126,227
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs