ITAC Assessment: UW2306
ITAC logo
ITAC Assessment: UW2306
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Commercial offset, small letter, and digital printing. Wide format printing
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 40,000
ft2
Annual Production 500,000,000
units
Production Hrs. Annual 6,783
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,010 881,899
kWh
Electricity Demand $33,001 4,125
kW-mo/yr
Electricity Fees $43,551 -
Natural Gas $10,855 1,026
MMBtu
TOTAL YEARLY COSTS $125,417
RECOMMENDED SAVINGS* $26,987 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7135: Install occupancy sensors $227 $344 $227
5,261
kWh
- -
02 2.4231: Reduce the pressure of compressed air to the minimum required $2,231 - $1,779
41,273
kWh
$452
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,732 $2,080 $3,772
87,512
kWh
$960
-
kW-mo/yr
-
04 2.4226: Use / purchase optimum sized compressor $9,916 $6,000 $7,906
183,437
kWh
$2,010
-
kW-mo/yr
-
05 2.3212: Optimize plant power factor $9,881 $14,306 - - $9,881
TOTAL RECOMMENDED $26,987 $22,730 $13,684
317,483
kWh
$3,422
-
kW-mo/yr
$9,881
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs